Naga Hammadi barrage

The barrage at Naga Hammadi stretches 320 meters over the Nile. It includes a seven bay sluiceway, two navigation locks, a public road bridge and a 64 mega watt hydro electric power plant.

This new barrage together with rehabilitated irrigation head-works will secure the livelihood of about two million people in Upper Egypt who depend on irrigated agriculture. This barrage will also improve navigation of the Nile river.

NSF's scope of work included supply and fabrication of steel piles for the barrage.

Approximate quantity

1600 tons.

Scope of work

  • Preparation of shop drawings as per specifications and data sheet. 
  • Supply and fabrication of carbon steel requirements for piles.
  • NDT requirements as per specifications.

Time of completion

Approximately 6 months.

 