Damietta LNG export terminal

The Damietta liquefied natural gas (LNG) terminal was the first LNG production and export complex in Egypt. The majority of the gas exported is used to supply ‘clean' gas-fired power stations in Spain. The single train facility, which is the largest in the world, is capable of producing 5 million tons of LNG annually.

Our scope involved the fabrication and delivery of steel tubular piles and steel structure for the LNG export jetty.

Approximate quantity

10,000 tons of steel piles and 3,500 tons of steel structure.

Scope of work

  • Preparation of shop drawings as per specifications and data sheets.
  • Supply, fabrication and delivery of steel structure and tubular piles.
  • Hot dipped galvanized steel structure.
  • 100% radiographic tested tubular piles.
  • NDT requirements.

Time of completion

Approximate 10 months.

 